Notice Type

Employer's Risks: FIDIC Clause 17.3 Notice Guide

This guide walks through FIDIC Clause 17.3 — the list of Employer's Risks under the 1999 Red Book — and Sub-Clause 17.4, which sets out what the Contractor actually recovers when one of those risks damages the Works or delays completion.

War, an Employer's early occupation of finished sections, a design the Employer's own personnel supplied — these sit outside the Contractor's control, but FIDIC does not treat them the same way. Six of the eight named risks pay Cost only; two pay Cost plus profit. Getting that wrong means the notice either under-claims or over-reaches. This guide covers what the eight risks are, why the entitlement splits, and how to draft a notice that survives scrutiny.

What Clause 17.3 Covers

Sub-Clause 17.3 of the 1999 Red Book lists eight events and circumstances the Contract treats as Employer's Risks — meaning the Employer, not the Contractor, bears the consequences if one of them damages the Works, Goods, or Contractor's Documents, or delays completion:

The first five sit close to Force Majeure or Exceptional Event territory — war, terrorism, radiation — but Clause 17.3 treats them as risk allocation for damage to the Works, separate from the broader relief from performance under Clause 19 (1999) or Clause 18 (2017). The last three are mixed: unforeseeable natural forces is another shared, no-fault risk, while the Employer's own use of the Works and Employer-supplied design are things the Employer itself did or chose, not external catastrophes.

💡

Key Takeaway: Employer's Risks cover eight distinct events. Six are shared, no-fault risks — war, terrorism, riot, radiation, aircraft pressure waves, and unforeseeable natural forces. Two — the Employer's own use of the Works and design supplied by the Employer's Personnel — are risks the Employer created directly.

The Entitlement: Time, and Sometimes Profit

Sub-Clause 17.4 sets out the consequences, and the entitlement is not a single figure that applies across all eight risks the same way.

If the Contractor suffers delay from an Employer's Risk event, or incurs Cost rectifying loss or damage one of them caused, the Contractor is entitled — subject to notice under Sub-Clause 20.1 — to an Extension of Time under Sub-Clause 8.4. That part is uniform. Cost recovery is where the clause splits. War, terrorism, riot, munitions and radiation, aircraft pressure waves, and unforeseeable natural forces give Cost only — shared, no-fault risks that neither party profits from putting right. The Employer's use or occupation of the Works, and design provided by the Employer's own Personnel, are different: the Contractor recovers Cost plus reasonable profit, commonly cited at around five percent. These two are not shared risks — they are things the Employer itself did, so it is treated as at fault in a way it is not for a riot or a radiation leak it did not cause.

💡

Key Takeaway: Every Employer's Risk event supports an Extension of Time. Cost recovery splits: war, terrorism, riot, radiation, aircraft pressure waves and unforeseeable natural forces get Cost only. The Employer's own use of the Works and Employer-supplied design get Cost plus reasonable profit, because those two are risks the Employer created rather than shared no-fault events.

When to Notify

The notice mechanism runs through Sub-Clause 20.1, the same procedural gateway that governs every FIDIC claim. The Contractor must give notice within 28 days of becoming aware, or when it should have become aware, of the event or circumstance giving rise to the claim. A prudent timeline:

Some Employer's Risk events are a single moment — a pressure wave, an act of occupation. Others run for weeks — an extended occupation, an unresolved security incident. Where the event is ongoing, the 28-day clock still starts when the Contractor realises it will affect the Works, not when the event ends. Waiting to see how bad it gets before notifying is the most common way a 17.3 claim is time-barred.

💡

Key Takeaway: The 28-day clock runs from awareness of the event's effect on the Works, not from when the event ends. An extended occupation or an ongoing incident still needs a notice within 28 days of the Contractor realising it will cause delay or Cost, followed by updates as the position develops.

Evidence You Need

A Clause 17.3 claim is won or lost on these evidence trails:

Classification evidence is the step Contractors skip most often — "the Employer moved in early" feels obvious in the moment. Written down and pinned to the correct sub-paragraph, it tells the Engineer which entitlement applies before the Cost figures are even discussed.

💡

Key Takeaway: Classification evidence decides which entitlement is available. For a use-or-occupation or design claim, keep the paper trail that proves the Employer's own act — an occupation date, a design instruction bearing the Employer's Personnel's name — because that is what unlocks profit on top of Cost.

How to Structure the Notice

A robust notice should include:

Specificity carries this notice. "The Employer took possession and beneficial use of the completed Substation Building on 14 August 2026, ahead of the Taking-Over Certificate and without agreement recorded under the Contract" is verifiable in an afternoon. "The Employer has been using parts of the Works" is not.

💡

Key Takeaway: Name the specific sub-paragraph and event precisely, state what was lost or delayed, and reserve profit only where the Employer's own act — occupation or design — is the ground relied on. A notice that identifies the exact sub-paragraph moves faster than one that just says "Employer's Risk."

Common Mistakes With 17.3 Notices

💡

Key Takeaway: The recurring errors are claiming profit under the wrong ground, failing to identify the specific sub-paragraph, confusing this clause with Force Majeure or weather delay, late notice, and missing the act-of-Employer evidence that profit claims depend on.

Frequently Asked Questions

What does FIDIC Clause 17.3 actually cover?

Sub-Clause 17.3 of the 1999 Red Book lists eight events and circumstances the Contract treats as Employer's Risks: war and invasion; rebellion, terrorism, and civil war; riot or commotion by persons other than the Contractor's Personnel; munitions, explosives, or radiation; pressure waves from aircraft; the Employer's use or occupation of the Permanent Works; design supplied by the Employer's Personnel; and unforeseeable operations of the forces of nature. If one of these damages the Works or causes delay, the Employer bears the consequences rather than the Contractor.

Does every Employer's Risk event entitle the Contractor to profit?

No. All eight support an Extension of Time where they cause delay, but Cost recovery splits. War, terrorism, riot, munitions and radiation, aircraft pressure waves, and unforeseeable natural forces get Cost only. Only two grounds — the Employer's own use or occupation of the Works, and design supplied by the Employer's Personnel — get Cost plus reasonable profit, since those are risks the Employer created rather than shared, no-fault events.

What's the difference between an Employer's Risk and Force Majeure or an Exceptional Event?

They overlap on some named events — war and terrorism appear in both — but serve different purposes. Clause 17.3 allocates the risk of damage to the Works and the resulting Cost and time consequences. Force Majeure (Clause 19, 1999) or an Exceptional Event (Clause 18, 2017) is broader: it can relieve a party from performing its obligations altogether, and in some circumstances lead to termination. Cite the clause that actually matches what happened and what relief is sought.

What is the notice deadline for a Clause 17.3 claim?

The same 28-day rule that governs every FIDIC claim applies, running through Sub-Clause 20.1: notice must be given within 28 days of the Contractor becoming aware, or when it should have become aware, of the event and its effect on the Works. Detailed particulars follow within 42 days under the 1999 Red Book, with continued updates for as long as the event's effects are ongoing.

Where did Employer's Risks move to in the FIDIC 2017 Second Edition?

The 2017 Second Edition restructured Clause 17. The Employer's Risks list is folded into Sub-Clause 17.2 (Liability for Care of the Works) rather than sitting in its own 17.3, and 17.3 in the 2017 numbering covers a different subject, Intellectual and Industrial Property Rights. Always confirm numbering against the specific edition and any Particular Conditions in play.

Authoritative Sources

This guide reflects the FIDIC Conditions of Contract and established construction-law authority. For the primary materials, see:

Muhammad M. Jiwani, Project Director

About the Author

Muhammad M. Jiwani is a Project Director with 15 years' experience on major infrastructure and energy projects administered under FIDIC contracts. He writes from first-hand experience serving notices and managing contractual claims on live projects.

Try ChatNotice now.

Book a demo