Essential

FIDIC Notice to Correct (Clause 15.1): How to Respond

It arrives on a Sunday evening, copied to head office: a letter from the Engineer headed "Notice under Sub-Clause 15.1", listing failures and demanding they be made good within 14 days. Half the Site team wants to fire back a furious rebuttal; the other half wants to ignore it as posturing. Both instincts are wrong. A notice to correct is the first formal step on the road to termination, and the response — in substance and in writing — decides which way that road runs.

What a Notice to Correct Is

Under Sub-Clause 15.1 of the FIDIC 1999 Red Book, if the Contractor fails to carry out any obligation under the Contract, the Engineer may give a notice requiring the Contractor to make good the failure and to remedy it within a specified reasonable time.

On its face it is a housekeeping clause — a formal way of saying fix this. What gives it teeth is the clause next door: under Sub-Clause 15.2(a), failure to comply with a notice to correct is a ground on which the Employer may terminate the Contract. That is why an experienced Contractor treats a 15.1 notice differently from ordinary site correspondence. Ordinary letters argue about money. This one is the loaded gun on the wall — most never go off, but every one of them can.

The 2017 Second Edition keeps the mechanism and tightens the drafting: the notice must describe the failure, state the Sub-Clause under which the obligation arises, and specify a reasonable time for the remedy. That checklist matters to both sides, as the next section shows.

💡

Key Takeaway: A notice to correct is the Engineer's formal demand under Sub-Clause 15.1 to remedy a contractual failure within a specified reasonable time — and non-compliance is a termination ground under Sub-Clause 15.2. Treat it as a legal document, never as routine site correspondence.

What Makes a Notice to Correct Valid — and Invalid

Because termination can hang off it, courts read a 15.1 notice strictly. The leading case is Obrascon Huarte Lain v Attorney General for Gibraltar — a FIDIC tunnel project where the validity of the notice to correct was fought all the way through the termination. Out of it come the working tests:

This cuts both ways. An Employer who terminates on the back of a vague or unreasonable notice has built the termination on sand, and wrongful termination is among the most expensive mistakes in construction. A Contractor who receives a defective notice holds a strong card — but holding a card is not the same as ignoring the game, which is where the response comes in.

💡

Key Takeaway: A valid 15.1 notice names a specific, real contractual failure and allows a time that is reasonable as at the date of the notice — vagueness or an impossible deadline undermines it, and any termination built on it. Judged strictly, because termination hangs off it.

How to Respond: Two Tracks, Run Together

The right response runs on two tracks at once — one on the ground, one on paper.

On the ground: if any part of the alleged failure is real, start fixing it now, visibly, and document the fixing. Nothing defuses a 15.1 notice like compliance. The goal is that by the specified date, either the failure is remedied or there is unarguable evidence of diligent progress toward remedying it.

On paper, respond in writing, well inside the specified time:

💡

Key Takeaway: Respond on two tracks: remedy the real failures visibly and fast, while a written reply accepts what is true, disputes what is not, challenges any defect in the notice, and serves the Contractor's own 20.1 notices for Employer-caused items. Never silence; never a blanket admission.

Response Letter Template — Copy and Adapt

Here is a skeleton for the written track. Replace everything in square brackets, and be precise about which items are accepted and which are disputed — that split is the whole letter.

[Date] To: [Engineer's name and company] Project: [Project name and contract reference] Response to Notice under Sub-Clause 15.1 dated [date of notice] The Contractor acknowledges receipt on [date of receipt] of the Engineer's notice under Sub-Clause 15.1 and responds as follows. Item [1] — [alleged failure as described in the notice]: The Contractor accepts that [describe the matter accurately and narrowly]. Remedial action commenced on [date] and will be completed by [date], as follows: [remedy plan in brief]. Item [2] — [alleged failure]: The Contractor does not accept that this constitutes a failure to carry out an obligation under the Contract, because [reason — e.g., no obligation under the cited Sub-Clause requires this; the matter arises from [the Employer's / the Engineer's] act or omission, namely [describe], in respect of which the Contractor refers to its notice under Sub-Clause 20.1 dated [date] / has today given notice under Sub-Clause 20.1]. The Contractor further notes that the time specified in the notice is [not reasonable in the circumstances, because — state why briefly] and proposes [date] as a reasonable date for completion of the remedial actions accepted above. This response and the actions described are without prejudice to, and with full reservation of, the Contractor's rights under the Contract and at law. Yours faithfully, [Name] [Designation, for the Contractor]

Serve it by the contract's notice method, keep the proof of delivery, and diarise the specified remedy date — that date, not the letter, is what Sub-Clause 15.2 will be tested against. And if any item calls for a counter-notice under Sub-Clause 20.1, that is a notice ChatNotice can draft for you in minutes — it is the one part of this response with its own unforgiving 28-day clock.

💡

Key Takeaway: Answer item by item — accept narrowly with a dated remedy plan, dispute with clause-referenced reasons, question an unreasonable time, and reserve all rights. Serve it by the contractual method and diarise the remedy date; that date is what termination would be tested against.

Common Mistakes on the Receiving End

💡

Key Takeaway: Six responses lose this fight: saying nothing, angrily disputing everything, admitting everything to keep the peace, fixing the failures without keeping evidence, missing your own Sub-Clause 20.1 counter-notice, and agreeing a new deadline only verbally. Each one hands the Employer a stronger termination file than the original failure did.

Frequently Asked Questions

What is a notice to correct under FIDIC?

Under Sub-Clause 15.1 of the FIDIC 1999 Red Book, if the Contractor fails to carry out an obligation under the Contract, the Engineer may give a notice requiring the Contractor to make good the failure and remedy it within a specified reasonable time. It is a formal contractual warning — and it matters because failure to comply with a notice to correct is a ground on which the Employer may terminate the Contract under Sub-Clause 15.2.

Can the Employer terminate immediately after a notice to correct?

No. The notice to correct must specify a reasonable time for the Contractor to remedy the failure, and termination under Sub-Clause 15.2 only becomes available if the Contractor fails to comply with the notice. Under the 1999 forms the Employer must then give 14 days' notice of termination. A termination built on an invalid notice to correct — vague failure, unreasonable time — is itself exposed to challenge as wrongful termination.

What makes a notice to correct invalid?

Case law on Clause 15.1 — notably Obrascon Huarte Lain v Attorney General for Gibraltar — establishes that a notice to correct must relate to an identifiable, specific contractual failure, and the time allowed must be reasonable, judged at the date the notice is given. A notice that recites vague dissatisfaction with progress, fails to identify what obligation was breached, or sets an impossible deadline is open to challenge.

How should a Contractor respond to a notice to correct?

In writing, quickly, and on two tracks at once. First, take the notice seriously on the ground: if the failure is real, start remedying it and show the plan. Second, protect the record: confirm receipt, state precisely what is accepted and what is disputed, challenge any failure that is not an actual contractual obligation or any time that is unreasonable, and reserve rights. If the alleged failure traces back to an Employer or Engineer cause, serve the corresponding Sub-Clause 20.1 notice — silence forfeits that position.

Does a notice to correct apply under the FIDIC 2017 forms too?

Yes. The 2017 Second Edition keeps the notice to correct in Sub-Clause 15.1 and tightens it: the notice must describe the Contractor's failure, state the Sub-Clause under which the obligation arises, and specify a time for remedy that is reasonable in the circumstances. The tightened wording cuts both ways — it gives Employers a checklist, and it gives Contractors clearer grounds to challenge a notice that skips any element.

Authoritative Sources

This guide reflects the FIDIC Conditions of Contract and established construction-law authority. For the primary materials, see:

Maisam Jiwani, Project Director

About the Author

Maisam Jiwani is a Project Director with 15 years' experience on major infrastructure and energy projects administered under FIDIC contracts. He writes from first-hand experience serving notices and managing contractual claims on live projects.

Never miss a 28-day deadline again.

Get Started